Since 1 October 2026, a building control approval application to the Building Safety Regulator that creates homes or student bedspaces has to carry building safety levy information. Here is what regulation 17A asks for, and what follows later in the project.

Check your application pack → Free, runs in your browser, nothing uploaded.

What changed on 1 October 2026

The Building Safety Levy (England) Regulations 2025 (SI 2025/1236) added a new item to the information a Gateway 2 application must include: regulation 4(1)(f) for new higher-risk buildings and regulation 12(1)(f) for work to existing ones. It applies where the work provides one or more dwellings, or bedspaces in purpose-built student accommodation (PBSA), in a residential building. The application must then include the building safety levy information set out in regulation 17A of SI 2023/909.

The BSR collects the information and passes it to the local council or other collecting authority, which decides whether a levy is due and how much. The BSR's guidance says applications without the required levy information can be rejected.

Which applications it applies to

What the levy information must include

Regulation 17A(1) lists:

  1. a statement of whether the work is development that needs planning permission, or to which section 33 of the Planning Act 2008 applies;
  2. where planning permission is needed, its status, from one of these:
    • granted, identifying the permission;
    • applied for but not yet determined, identifying the application;
    • not yet applied for;
    • subject to prior approval, with the requirement satisfied or an application made or not yet made.
    For a permission that allows phased development, this refers to the phase or phases the application covers;
  3. a statement of whether the work is, or is expected to be, major residential development, or part of a wider development that is;
  4. for each building in the work, the local authority the building is in;
  5. the number of dwellings the work will provide;
  6. for PBSA, the number of bedspaces;
  7. for a variation application, details of any levy determination notice already given.

Where the work is part of a wider development, the planning questions in (a) to (c) refer to the whole development, not just this application.

Work to existing buildings

For work to an existing higher-risk building, the levy information is required in a regulation 12 application where the work provides dwellings or PBSA bedspaces. For category B work, regulation 12(3)(b) asks only for items (1)(a) to (e) of regulation 12, so the levy item isn't on the list. Work that changes the number of flats or residential rooms is category A anyway. See Gateway 2 for work to existing buildings.

Change control applications

Where the original application was made on or after 1 October 2026, a change control application for work that provides dwellings or PBSA bedspaces in a residential building must also include levy information for the updated application (regulation 21(2)(g)). Where the levy charging conditions are met, it must also include levy charging information, such as floorspace figures. If a commencement notice has already been given, the planning statements in 17A(1)(a) and (b) aren't needed again. Change control applications on projects whose application was submitted before 1 October 2026 aren't caught by the levy. More on changes: major and notifiable changes after Gateway 2.

To estimate the amount, use the free building safety levy calculator.

What comes later: commencement and completion

Checking your pack

The free Gateproof checker now looks for a levy statement in regulation 4 applications (new higher-risk buildings), and in regulation 12 applications when you tick the levy option. It reports whether it can find a planning status statement, the major residential development statement, and the local authority and dwelling or bedspace numbers close to the levy wording. It's a keyword screen: it shows that wording is present, not that the statements or figures are right, so check them yourself. The full list of requirements is in the Gateway 2 checklist.

Sources

Written on 14 October 2026 and paraphrased from the sources above. Levy rates and exemptions are in the GOV.UK guidance. Check the current text before relying on this page. This is general information, not legal, tax or compliance advice. Contains public sector information licensed under the Open Government Licence v3.0.