Gateway 3: the completion certificate

When building work on a higher-risk building is complete, the client must apply to the Building Safety Regulator for a completion certificate, or for a partial certificate before any part is occupied early. Here is what a full application must contain, as a 31-item checklist, and what the BSR checks.

Check your Gateway 2 pack → The free checker screens Gateway 2 packs. The agreed documents it checks come back at Gateway 3.

Where things stand

In its data as of 31 August 2026, the BSR reported 346 Gateway 3 applications received. 260 of them were for internal refurbishments, and most of the rest were transitional cases (45) and NHS internal refurbishments (23). No new-build project that went through Gateway 2 had reached Gateway 3 yet. Over the previous 12 weeks it determined 16 applications, approving 88%, with a median determination time of 20 weeks. The quickest was 7 weeks. The legal limit is 8 weeks from receipt of a valid application, and it can be extended by written agreement (regulation 41). The BSR doesn't say how its median is measured, and 16 is a small sample, but the gap is a reason to plan for a long wait. The BSR also said its inspections of new-build projects had found "a small amount of building work that deviates from designs agreed in gateway 2" (BSR building control approval application data, June to August 2026).

What the BSR checks

Under regulation 44, the BSR approves the application only if it is satisfied, after taking all reasonable steps, that:

Otherwise it must reject the application. Before that, an application that doesn't contain everything regulation 40 requires is invalid, and the BSR sends a notice giving the reasons (regulation 41(2)–(3)). Its guidance says it compares the submitted documents with the documents approved at Gateway 2, reviews the change control log and any changes submitted during the build, and inspects the completed work. Where building safety levy information was required, the BSR must reject the application unless the collecting authority has confirmed the client's levy liability statement (regulation 44(2A)). That means the levy has been paid, or a notice of no charge has been given.

The checklist

For a full completion certificate. Paraphrased from regulations 38 and 40 of SI 2023/909 (as amended from 1 October 2026) and the BSR's guidance. These requirements don't apply to work to an existing building that is only scheme work, exempt work or emergency repairs under regulation 10.

The application (regulation 40(1)) (15)

Documents that go with it (regulation 40(2)–(3)) (8)

Handover to the building's owner or manager by completion (regulation 38) (3)

Also expected by the BSR (5)

Where it goes wrong

Partial completion certificates

If any part of the building is to be occupied before all the work is complete, the client must apply for a partial completion certificate before that occupation (regulation 45). This is a separate application. It follows the partial completion strategy submitted with the Gateway 2 application, and the BSR's guidance says changes to that strategy must be submitted to the BSR. On top of most of the items above, applied to the part concerned, it needs:

After the certificate

A higher-risk building with at least two residential units must be registered with the BSR before people live there, and a completion certificate is needed to register it. A rejection can be reviewed by the BSR and then appealed to the First-tier Tribunal. The charges for full and partial certificates are in the BSR charging scheme, and the BSR won't issue a certificate while charges on the building control approval application are overdue.

Sources

Written on 14 October 2026 and paraphrased from the sources above. Check the current versions before relying on it. This is general information, not legal or compliance advice. Contains public sector information licensed under the Open Government Licence v3.0.